Combined earthwork, grading, and underground utility packages that take a raw Las Vegas Valley parcel from vacant land to a fully serviced, construction-ready pad. Tell us about your project and we'll match you with a vetted, licensed local contractor — free.
Many Las Vegas Valley developers prefer a single contractor to handle grading and all underground utilities together, since the sequencing between these scopes is tightly linked. A full site development package typically includes:
Need detail on a specific piece of this? See our dedicated pages for earthwork & grading, sewer line installation, water line installation, and storm drain & drainage.
On a typical Las Vegas Valley project, rough grading establishes stable, accessible ground; sanitary sewer generally goes in first since it relies on gravity flow and is often the deepest line; storm drain and water follow; and fine grading finishes the site for paving and vertical construction. When one contractor manages this whole sequence, conflicts between trades — like utility trenches cutting through freshly graded subgrade — are far less common than when an owner is coordinating several separate contractors directly.
If you only need one specific scope — say, just a sewer connection or just grading — our individual service pages may be a better fit.
A combined grading-and-utility package on a mid-size Las Vegas Valley commercial site commonly takes several weeks to a few months from mobilization through final agency acceptance, depending on site size, soil conditions, and permitting timelines. See our costs & timelines guide for a full phase-by-phase breakdown and our permitting overview for what affects your schedule most.
Full site development (also called site preparation) refers to combining earthwork/grading with underground utility installation — sewer, water, and storm drain — under one coordinated scope, so the site is fully ready for vertical construction hand-off.
Because these phases are tightly sequenced — utilities generally go in after rough grading but before final grading and paving — a single contractor managing both reduces coordination gaps, scheduling conflicts, and finger-pointing between trades.
Contractors typically manage construction-phase permitting and inspections for the scopes they perform, though civil engineering plan preparation is usually handled by a separate civil engineer earlier in the process.
It varies by site size and scope, but a combined grading and utility package on a mid-size commercial site in the Las Vegas Valley commonly takes several weeks to a few months from mobilization to final acceptance. See our costs and timelines guide for a phase-by-phase breakdown.